Interior Work:
- Teachers were given access to set up classrooms.
- Classroom desks and chairs have been installed.
- Stage floor was painted and is awaiting its final coat.
- Auditorium sound system installation is underway.
- Auditorium carpet installation is nearly complete.
Exterior Work:
- Curb and gutter work at the main entrance iscomplete.
- Road base has been placed, with asphalt pavingunderway.
- Concrete sidewalks and surrounding plaza areas arecomplete.
- Landscaping work continues.
- Preschool playground equipment and thesurrounding security fencing is complete.
Building Compliance:
- Granite School District issued a TemporaryCertificate of Occupancy to allow outside vendorsand GSD personnel in the building to perform theirremaining work.